This morning we passed our inspection on the new side of the building! We have our certificate of occupancy!
I would like to thank everyone who volunteered their time and effort to make this happen. There are too many to list here but please know, we couldn’t have done it without you. Your efforts have made us bigger and better and you deserve a round of applause!
Our next steps are as follows:
This weekend -
- Finish repairing the ceiling - the frame is done, just need to cut some tiles.
- Deep clean the floors - so the tape will stick… going to rent a cleaner for this or get a service
- Tape off the committee areas - we are getting a specific tape for this
- Paint the wall patches - there is a chart explaining what paint goes where if anyone wants to get on this just find one of us on the team and we can get you going.
Once this weekend’s chores are done - (Scheduled to start Monday, but can start based on task completion)
- Electronics, Science and Vector begin moving
- Place final security cameras
- Glass and Print Making begin moving
- Logistics adds work tables to the new front room
- Clean the Electronics, Science and Vector areas
- 3D Fab moves it’s design computers to their area (The printers can’t move until we have the Phase 2 power done. Sorry)
Second phase moving - (Timing dependent on the tasks above)
- Common room moves to the new side
- Clean the common room
- Digital moves to old Electronics
- Clean Digital
- Conference room moves and gets cleaned
- CA moves to old Common Room/Digital/Conference Room
- Clean CA
- Warehouse side committees can bring their storage items to their new space prior to their official move
To the Chairs of each committee that will be in the early moves, I’ve already spoken with a few of you, I’ll be around tonight if you want to discuss in person, otherwise, just send me a PM and I can help you coordinate any moving assistance you may need.
Again, huge thanks to everyone that stepped up and made this possible! You are all ROCK STARS!