Hi all,
Here is the present status of all current projects around the space for construction:
-
North Lobby restroom: Urinal has been installed and is functional. We are waiting on plastic shims to come in this week to fix the wobble of the toilet.
-
Dark Room (former men’s room). Initial plumbing has been completed. We need to get a new steel sink procured and do renovations in there (fix flooring, remove stalls, patch drywall, etc.).
-
Phase 1 construction. We are currently waiting on glass from our vendor to install into the new lathe room and digital media. Current ETA is end of this week, possibly next week.
-
New Automotive. We need to get some plumbing and electrical work done, alongside replacing the garage door springs, now that the construction has been completed in order to accommodate the new lifts. Assuming no issues, the plan is to open new automotive by end of year.